Current Projects
In order to give you an overview of the range of our scaffolding services, we present current projects, the special features of the erected scaffolding and the benefits of the different scaffolding possibilities for our customers.
- Stena Line Kiel
- Congress Palace Kassel
- Areva Bremerhaven
- Bard Offshore Emden
- Nordstream Lubmin
- Sondermaschinenbau Wedel
Access to the restaurant on the Stena Line roof terrace at the Schwedenkai handling terminal
General Project Description
The regular steel stairway, which will provide access to the roof terrace of the Schwedenkai in the future, was not finished in time for "Kiel Week". To prevent a loss of image and of income in the area of the event, it was decided that access should be provided temporarily using a staircase tower.

- Using Layher's scaffolding system, Ostsee Gerüstbau erected staircase towers such as this one to the Stena Line Schwedenkai restaurant

- Advantages of a staircase tower by Ostsee Gerüstbau: can be set up quickly and for a short time only, can be rented and is secure
Type of scaffolding / scaffold
Ostseegerüstbau errected a staircase tower tailored specifically for the terminal building using Layher's scaffolding system.
The scaffolding structure is designed for events with a relatively high utility load – the staircase tower meets the highest possible safety requirements as specified according to local regulations for the set-up and operation of public assembly locations.
Special features of the scaffolding project and benefits for the customer
- short-term, fast set-up
- Adherence to legal regulations
- Individual tailoring of the staircase tower to local circumstances: turned 90 degrees with a rest platform
- child-safe railings
- flat steps; reduced stairway incline/step height tailored to the height between floors
- maximum stability by broadening the scaffolding and through concrete weights
- Verification of stability (statics)

- The Ostseegerüstbau staircase tower meets the strictest safety requirements according to the regulations for the set-up and operation of public assembly locations

- The stairway incline/step height of the staircase tower errected by Ostsee Gerüstbau was tailored according to the height between floors at the handling terminal
Extension

- The cantilevered cassette roof (41 x 41 m)
was designed
by Ostsee Gerüstbau in such a way that individual
cassettes can be removed so that components and
materials can be left in
General Project Description
A modern flat-roofed building is attached to the old, magnificent construction of the Congress Palace. Weather conditions and the onset of Winter delayed the construction so that it was decided from the considerations of costs and benefits to enclose the building with a tent structure.
Type of scaffolding / scaffold
Ostseegerüstbau erected a Winter construction: a 12 metres high scaffold which has been enclosed with weatherproof tarpaulins. The floating cassette roof with a span of 41 metres is a special design.
Special features of the scaffolding project and benefits for the customer
- All-round protection against snow, rain and wind
- Heat protection comparable with ISO single glazing inside the tent
- Construction work irrespective of weather and compliance with the schedule – loss of image for delayed construction is prevented

- Another advantage of the Ostsee Gerüstbau winter design: structural damages, water damages, etc. are eliminated and the building contractor's liability is reduced

- Advantages of a winter construction tent and cassette roof: All tradesmen can work regardless of weather conditions, and construction schedules can be adhered to. In this case: Installing insulation

- Ostsee Gerüstbau's winter construction guarantees material flow: All tradesmen can deliver their material unhindered. Flexible openings in the framing can be arranged, thereby facilitating material flow.

- During connection of the new structure to the existing palace, Ostsee Gerüstbau guarantees that all rainwater is diverted by means of its tent design
Protection of offshore wind energy prototypes

- Ostsee Gerüstbau sets up a winter structure
with shrink film as a tarp
General Project Description
Wind energy prototypes which should be used offshore in the future have been tested onshore. Their gondolas will now be removed for analysis purposes. In order to be able to assess the interior of the systems, they are protected by a Winter construction tent.
Type of scaffolding / scaffold
The Winter construction which Ostseegerüstbau erects around the gondolas is 15 x 15 metres, 8 metres high and has a prefabricated roof. The free-standing scaffold construction is designed for wind load zone 4. The air cushion film applied on the Winter film provides particularly good heat insulation.
Special features of the scaffolding project and benefits for the customer
- Wind and weather protection for the work on the open gondola (GFRP covering has been removed)
- Analysis directly onsite possible: expensive transport, required special authorisations and additional hall capacities at the production location no longer become necessary

- Tents with tarps in white and/or bright grey provides good lighting inside

- Tent construction with good lighting

- The scaffolding design and winter film with bubble wrap applied keeps the heat in the tent
Installation of the gondolas of wind turbines
General Project Description
The interior of the gondola is connected to the outer GFRP covering during the assembly of wind turbines. A working platform is needed for the occurring assembly work.
Type of scaffolding / scaffold
Ostseegerüstbau is erecting surface scaffolding (also platform scaffolding) inside the gondola for the installation of the GFRP covering. The design of the scaffolding has been specially developed – the scaffold is exclusively supported on its feet; all parts of the gondola (pumps, generator, electrical equipment) remain free.
Special features of the scaffolding project and benefits for the customer
- Parts of the gondola are freely accessible, so not have to bear any loads and are not worn
- Uninterrupted working for all trades
- Cost-effective and flexible: The surface scaffolding can easily be adapted to changed conditions and moved quickly
Gas transfer station of the gas pipeline

- Work safety tents in the pit of the gas
transfer station protect against flying
sparks during welding work
General Project Description
As a draught-free environment is needed for the safety-relevant welding work on the gas transfer station, it is protected by a tent. Safe access to sliders at different heights is also needed.
Type of scaffolding / scaffold
Inside the protective Winter construction tent, Ostseegerüstbau erected a scaffold with several working levels at different heights.
Special features of the scaffolding project and benefits for the customer
- Weather and heat protection
- Occupational safety and work safety
- for recurring activities over a long time period such as welding, the scaffolding is the best, safest and most flexible alternative – several work operations are possible simultaneously, excellent stability, protection using tent tarpaulins possible

- The winter tent set up by Ostsee Gerüstbau protects against cold, wind and weather

- Scaffolding enclosed in tarps offer safe access to sensitive work areas

- The gas transfer station puts different challenges on the design of the scaffolding
Expansion of special machine construction industrial operation

- From a scaffolding, Ostsee Gerüstbau
erects a free-standing stairwell as an
outdoor access
General Project Description
The company is extending the third floor of its company building. It arranged an outside access so that nobody has to pass through the existing production during the construction work.
Ostseegerüstbau erected a free-standing stair tower as anchoring to the existing building was not possible. A platform with the size 2.50 x 2.50 metres has been included at a height of 9 metres as additional supply and working level. A roof protects the steps against slipperiness.
Special features of the scaffolding project and benefits for the customer
- Protection of the trade secrets
- Material can be delivered and processed on the top working level: time and cost saving

- The scaffolding/the stairwell has a platform at an elevation of 9 meters as an additional work level

- Tower staircase: A celing protects the metal steps of the scaffolding against moisture and ice